Fence Installation Process: Permits, Prep and Timeline

The fence installation process runs from measuring and permits to the 811 utility locate, post setting and a final walkthrough, and this guide explains who does what and where the waiting happens.

10 min readPublished by GC Digital

Much of the fence installation process happens before a post goes into the ground. This guide covers the stages from the first site visit to the final walkthrough when you hire a professional: measuring, the contract, permits, HOA approval, the utility locate, post setting, inspection and the punch list.

Key takeaways

  • Much of the calendar time can be waiting (permit, HOA approval, the utility locate, materials), not building.
  • Permit rules are local. Minneapolis, Herriman and Colorado Springs require no building permit for fences 7 feet or lower, but Minneapolis says zoning still applies.
  • 811 is free, and the notice period varies by state: 2 full business days in Oregon and Colorado, 3 working days in Virginia. Utilities do not mark private lines such as sprinklers.
  • City approval and HOA approval are separate. Herriman, Utah says it does not enforce HOA rules.
  • How posts are set depends on the product and the site. Follow the manufacturer's instructions and ask which method is in the contract.

If you have not hired anyone yet, read how to choose a fence company first.

The fence installation process at a glance

The stages run roughly in this order, and some apply only to certain properties. Rows marked illustrative are general examples, not published figures, so ask your contractor for a written schedule.

StageWho handles itCalendar timeCrew days on site
Consultation, measure, quoteContractor and homeownerDays to a couple of weeks (illustrative)0
Contract and cancel windowBoth3 business days for covered in-home sales (FTC)0
HOA approvalUsually homeownerVaries; no national standard0
Permit review, if requiredPer the contractAbout 10 to 15 business days in Herriman, UT (over 7 feet)0
811 locateThe person digging2 full business days (OR, CO) to 3 working days (VA)0
MaterialsContractorVaries by product and supplier0
Posts setCrewSame dayOften day 1 (illustrative)
Concrete set before loadingCrewFast-setting mix: 4 hours (QUIKRETE); concrete-filled vinyl gate posts: 72 hours (CertainTeed)Gates may wait for a later visit
Rails, panels, gatesCrewAfter the concrete has setOften 1 to 3 days for a typical backyard (illustrative)
Inspection, where requiredCity inspectorHerriman asks for at least 1 business day noticeWaiting
Walkthrough and punch listBothSame day to a few days (illustrative)Partial day

Sources: Colorado 811, Oregon 811 and Virginia 811 (locate periods); Herriman City (permit review, inspection notice); Federal Trade Commission (cancel window); QUIKRETE and CertainTeed (concrete times). Long runs, rocky soil, slopes or masonry take longer.

Stage 1: Consultation, measuring and the property line

The contractor walks the line, notes the slope, places gates and measures total linear feet. Herriman City, Utah, says a permit site plan must show where the fence will sit and its length in linear feet.

Do not guess the property line. Colorado Springs tells residents to contact a licensed surveyor to find it. Minneapolis asks for found boundary monuments or a survey for permitted fences, and says online images such as Google Maps are not sufficient as site plans. See fence surveys and property line rules for more.

Stage 2: The contract and what it should say

The California Contractors State License Board advises that a contract detail the work, price, payment timing, who gets the permits and when the job will be finished, with date changes on a signed change order. For a fence, also write down:

  • Who pulls the permit, files the HOA application and places the 811 request.
  • Start and finish dates, and what happens if weather or an inspection causes a delay.
  • Gate sizes and hardware, and the post setting method.
  • Where soil from the post holes goes, and the payment schedule.

The Federal Trade Commission says its Cooling-Off Rule gives you three days to cancel certain sales made at your home, workplace or dormitory, until midnight of the third business day after the sale. A contract signed at a contractor's office may not qualify. California's board says a down payment should never exceed 10 percent of the contract price or $1,000, whichever is less (with a narrow bonding exception). That cap is California only.

Stage 3: Do I need a permit for a fence?

Sometimes. Each example below comes from one named city and is not a national rule.

The common 7-foot pattern, and why zoning still applies

Minneapolis says fences up to 7 feet high do not require a building permit but must comply with zoning, and that all fences require zoning review. Herriman and Colorado Springs also require a building permit only above 7 feet. Oakland adds a warning: an exemption does not authorize work that violates the code or other local laws, and planning or zoning permits may still be required.

When a permit is often required anyway

  • Taller fences. Minneapolis, Herriman and Colorado Springs require a building permit above 7 feet.
  • Pool barriers. Minneapolis says pool barrier fences of any height require building permits, with fences and gates at least 4 feet high and self-closing, self-latching gates.
  • Floodplains and rights-of-way. Austin requires a permit for a fence in a floodplain at any height, and for a residential fence over 6 feet along a City right-of-way.
  • Masonry. Oakland's exemption stops at 3 feet for concrete or masonry fences.

What plans the city may ask for

Austin asks for an application, a plot plan survey and a drawing of the fence design. Herriman requires plans stamped by a structural engineer for fences over 7 feet. Colorado Springs says fences may not block access to electric or gas meters, fire hydrants or Fire Department Connections.

Herriman says plan review takes approximately 10 to 15 business days for fences over 7 feet. That is one city's figure, and shorter fences in the cities above need no building permit.

Stage 4: HOA fence approval

In Florida, section 720.3035 of the statutes allows an association to review the location, size, type or appearance of an improvement only to the extent that authority is stated or reasonably inferred in its declaration or published guidelines. The section sets no approval deadline. Other states differ. Read your declaration and architectural guidelines, because they define what you must submit.

City approval does not replace HOA approval. Herriman says it does not enforce any HOA or CCR requirements. Get the HOA decision in writing before materials are ordered.

Stage 5: Call 811 before building a fence

Who should call, and how far ahead

The Common Ground Alliance's 811 Before You Dig site calls 811 free and national, says every dig requires a call or click, and lists installing fences. Oregon 811's tip sheet says it is the responsibility of the person digging to avoid damaging marked lines, and Michigan's MISS DIG 811 says that if you hire the work out, make sure your contractor contacts them. Ask for the ticket number, which Oregon says serves as proof of the call.

The notice period depends on the state. Colorado 811 says at least two full business days before you dig, not counting the day of notification. Oregon says digging can start once all utilities are marked and the 2 full business days have passed. Virginia 811 says at least 3 working days. MISS DIG adds that you cannot start before the start time on your request, even if all lines are marked.

Paint colors and the tolerance zone

Under the American Public Works Association color code, white marks proposed excavation, red is electric, yellow is gas, orange is communications, blue is potable water, purple is reclaimed water and irrigation, and green is sewer. The national homeowner page says to avoid digging within 18 to 24 inches on all sides of utility marks. Colorado 811 says to dig with hand tools within 18 inches of a mark, and Oregon 811 uses 24 inches on either side.

What 811 does not mark

Virginia 811 says the water line from the meter to your house is private and will not be marked, and gives this rule: if a utility is installed from the meter to another location on your property, it will not be marked. Between them, Virginia 811, Colorado 811 and New York 811 list private lines such as:

  • Sprinkler and irrigation systems, and landscape lighting.
  • Invisible pet fence wire.
  • Electric lines to sheds or detached garages.
  • Gas lines to grills and fire pits, propane lines and septic tanks.

Colorado 811 says locating these is the owner's or excavator's responsibility at their own expense, and that private locate services average $100 to $350 in Colorado, which is not a national price.

Stage 6: Material lead times

Lead times depend on the product and supplier, so ask for the order date and expected delivery in writing. See how long a fence lasts for help with material choice.

Stage 7: Install days, step by step

Post holes: diameter and depth

After the crew strings the line and checks the 811 marks, the manufacturer's instructions set hole sizes. QUIKRETE says the hole should be three times the width of the post, with a depth of 1/3 to 1/2 of the above-ground post length plus 6 inches. CertainTeed's vinyl fence guideline says to dig holes 30 inches deep or to the frost line, and bases its concrete figures on 12-inch holes for 5x5 posts and 10-inch holes for 4x4 posts. Each applies to its own product.

Frost depth

CertainTeed tells installers to check local codes for frost line depth, which varies widely. Minnesota's building code, for example, sets the minimum footing depth due to freezing at five feet in Zone I and 3-1/2 feet in Zone II. That rule is for building footings, not fence posts, but it shows why manufacturers say to dig to the local frost line.

Should fence posts be set in concrete?

  • Concrete. CertainTeed says all of its vinyl posts require concrete. Grant Kirker of the USDA Forest Products Laboratory wrote in the Journal of Light Construction that concrete reduces lateral post movement, and advised sloping the top away from the post to shed water, since ground level is where decay is most likely.
  • Concrete over gravel. QUIKRETE says to put 6 inches of gravel or crushed stone under the concrete. San Diego's fence bulletin calls for 12-inch concrete footings over 3 inches of loose gravel for wood posts.
  • Backfill without concrete. A European study Kirker cited compared concrete with gravel and dirt fills and rated concrete best for longevity. If a contractor proposes no concrete, ask why and how it affects the warranty.

CertainTeed says techniques vary by region and to check local requirements, so the manufacturer's instructions and local rules come first. Its table calls for about twice as much concrete at gate posts as at line posts (285 versus 140 pounds for a 6-foot fence on 5x5 posts). For wood, Kirker notes UC 4B treatment is required for harsh below-ground exposure in wet or high-decay areas. See cedar vs pressure-treated fences.

Curing, panels and gates

QUIKRETE says its Fast-Setting Concrete Mix sets in about 20 to 40 minutes, and its post-setting instructions say heavy weight can go on after 4 hours under normal curing conditions. That applies only to that product. CertainTeed says a gate on a vinyl post filled with concrete and rebar should stay on blocks for 72 hours, one reason gates may go on during a later visit.

Stage 8: Inspection

Minneapolis says inspections are required for all building permits. Herriman requires a footing inspection before the concrete is poured plus a final inspection, requested at least one business day ahead, so holes can sit open until the inspector has seen them. Ask who requests inspections and how they affect the schedule.

Stage 9: Final walkthrough and punch list

Walk the whole line before final payment.

  • Posts plumb and evenly spaced, with a consistent top line.
  • Concrete finished below grade or sloped away from posts, as specified.
  • Gates swing freely, clear the ground and latch every time. Pool gates close and latch on their own.
  • Meters, cleanouts and hydrants not blocked, and any required permit finaled.
  • Lawn or sprinkler damage fixed, spoil removed, and warranty papers received.

How to prepare for fence installation

  • Put pets away and give locators access. Oregon says you do not have to be home for the locate.
  • Mark private lines that utilities will not mark, or hire a private locator.
  • Confirm the 811 ticket number and start time with your contractor.
  • Have written HOA approval and any permit in hand before install day.

Frequently asked questions

How long does it take to install a fence?

The build is often the short part and the waiting the long part. The 811 notice period is 2 to 3 business days in the states cited here, and Herriman, Utah quotes about 10 to 15 business days of plan review for fences over 7 feet. Crew time depends on the run, soil and slope, so ask for a written schedule.

Do I need a permit for a fence?

In cities such as Minneapolis, Herriman and Colorado Springs, a fence 7 feet or lower usually does not need a building permit, but zoning rules still apply. Those cities and Austin require permits in cases such as taller fences, pool barriers, floodplains and rights-of-way. Check your own city's fence page.

Do I have to call 811 if I hire a contractor?

Oregon 811 says the person digging is responsible for avoiding marked lines, and Michigan's MISS DIG says to make sure your contractor contacts them. The service is free. Ask for the ticket number, and wait for the start time even if marks are down.

Does 811 mark sprinkler lines and invisible dog fences?

No. Virginia, Colorado and New York 811 list them as private lines that utilities do not mark. Mark them yourself or hire a private locator, which Colorado 811 says averages $100 to $350 in its state.

Should fence posts be set in concrete?

Follow the manufacturer's instructions and local rules. CertainTeed requires concrete for its vinyl posts, and a USDA Forest Products Laboratory researcher says concrete reduces post movement. QUIKRETE and San Diego put gravel under the concrete.

Do I need HOA approval, and is it the same as a permit?

They are separate. Herriman says it does not enforce HOA rules, so you may need both. In Florida, an association's review power is limited to what its declaration or guidelines say.